Parkes Sewage Treatment Plant

CLIENT: JOHN HOLLAND GROUP PTY LTD

LOCATION: AKUNA ROAD PARKES

TIME FRAME: 18 MONTHS

PROJECT: The Parkes Sewage Treatment Plant project commenced in February 2016 to build a new facility that would provide Parkes with a reliable, robust & energy efficient sewage service that would replace Parkes existing service by slowly transitioning from the old to the new.

Steve Magill Earthmoving Pty Ltd has provided earthworks to develop the site over an 18 month period including;

  • site clearing
  • hard stand area
  • main access road
  • all underground civil pipe work
  • all underground electrical trenches
  • all civil works to complete AWARF, bulk excavation, underground pipework, lagoon construction, road construction.